By Eng. Anwar Ali Khan, MSc (Structural), PE – Civil & Structural Engineer (SCE member) · Version 1.0 (draft) · Last reviewed: 15 Nov 2026

Draft – under verification. Results are being cross-checked against hand calculations and verified spreadsheets. An engineer must check all results before use.

Results

Code checks

    Drawing (live)

    Table

    Step-by-step working

    ItemCheck / formulaValueReference
    Did this tool help?

    Plaster

    Wet volume is area × thickness. Multiply by about 1.27 for the dry loose volume (more mortar fills joints and surface hollows), add wastage, then split by the mix ratio. 100 m² of 12 mm plaster in 1:4 needs 1.2 × 1.27 × 1.05 = 1.60 m³ of dry materials: 461 kg of cement (10 bags) and 1.28 m³ of sand.

    Tiles, adhesive and grout

    Tiles per m² = 1/((L + j)(W + j)). Add 5–10% wastage (more for diagonal laying or small rooms), then round up to whole boxes. Adhesive is a rate per m² from the product sheet. Grout uses the standard formula kg/m² = (L + W)/(L × W) × tile thickness × joint width × 1.6.

    Paint

    Litres = area × coats ÷ coverage per coat. Emulsion typically covers 10–12 m²/L per coat on smooth plaster, less on rough or absorbent surfaces. Primer is usually one coat, and wall putty (if used) is about 1 kg/m² for two thin coats.

    FAQ

    Why 3.64 litres per gallon?

    Paint in Pakistan and the Gulf is commonly sold in 3.64 L “gallon” tins. Divide the litres by 3.785 for US gallons.

    Should I deduct openings?

    Yes for large openings. Many estimators deduct only openings over about 0.5 m² for plaster and paint, since reveals and edges use extra material.